Purchase Order Template: What Every Business Should Track
Purchase Order Template: What Every Business Should Track
By Abdullah Al Noman

This post is for anyone who sends purchase orders from a Word document, an email or a spreadsheet tab, and wants to know whether the template is missing something.
The short answer: a purchase order has three jobs. It tells the supplier exactly what you want, it records what you agreed (so you can check the bill against it), and it gives your own team something to receive against. A field belongs on the PO if it serves one of those three jobs. Below is the full template, then an example, then the five fields small businesses most often leave out.
The Template
Header
| Field | Why it is there |
|---|---|
| PO number | Unique, sequential. The supplier puts it on the delivery note and the bill, which is how you match them later |
| PO date | Starts the lead-time clock |
| Your company name, address, tax ID | Legally needed on many bills; tells the supplier who is buying |
| Supplier name, address, tax ID | So there is no doubt which entity you are buying from |
| Supplier contact | Who you are dealing with |
| Your contact (buyer) | Who the supplier calls with questions |
| Delivery address | Which warehouse or site, if you have more than one |
| Requested delivery date | When you need it |
| Payment terms | For example, 30 days from invoice. Agreed now, not argued later |
| Delivery terms | Who pays freight, who owns the goods in transit (for example, delivered to your door, or ex works) |
| Currency | Essential if you buy from abroad |
| Reference | The customer order or project this is for, if any |
Lines
| Field | Why it is there |
|---|---|
| Line number | So "line 3 was short" means one thing |
| Your item code | How your team identifies it |
| Supplier's item code | How the supplier identifies it. Prevents the wrong variant |
| Description | Size, grade, colour, specification. Enough that a stranger would pick the right item |
| Quantity | The number ordered |
| Unit of measure | Units, boxes of 50, metres, kilograms. Never leave it implied |
| Unit price | Agreed price per unit of measure |
| Discount | If any, per line |
| Tax rate | Per line, since rates can differ |
| Line total | Quantity x unit price, after discount, before tax |
| Requested date per line | If lines are needed at different times |
Footer
| Field | Why it is there |
|---|---|
| Subtotal, tax, total | The amount you are committing |
| Approved by, date | Proves the spend was authorised |
| Special instructions | Packing, labelling, certificates required, delivery hours |
| Terms reference | Link to your standard purchase terms, if you have them |
A Filled-In Example
PO-2026-0187, dated 6 October 2026
Supplier: a regional steel stockist. Delivery to: Warehouse 2. Requested: 17 October. Payment: 30 days from invoice. Delivery: delivered, supplier pays freight. Currency: KRW. Reference: customer order SO-0912.
| Line | Our code | Supplier code | Description | Qty | Unit | Unit price | Line total |
|---|---|---|---|---|---|---|---|
| 1 | ST-FB-50x6 | FB506-6M | Flat bar, mild steel, 50 x 6 mm, 6 m lengths | 40 | length | 21,500 | 860,000 |
| 2 | ST-RB-20 | RB20-6M | Round bar, mild steel, 20 mm, 6 m lengths | 25 | length | 18,200 | 455,000 |
| 3 | ST-PL-3 | PL3-1225 | Plate, mild steel, 3 mm, 1250 x 2500 | 6 | sheet | 96,000 | 576,000 |
- Subtotal: 860,000 + 455,000 + 576,000 = 1,891,000
- VAT 10%: 189,100
- Total: 2,080,100
Approved by: operations manager, 6 October. Special instructions: mill certificates required for line 3. Deliveries 8:00 to 16:00 only.
Notice what makes this PO checkable later: the unit is a length or a sheet, not "pcs"; the supplier code removes doubt about the variant; and the reference to SO-0912 tells your team which customer is waiting.
The Five Fields Small Businesses Leave Out
1. Unit of measure. "40" of what? Forty 6-metre lengths, or forty metres? This one field causes more receiving errors and billing disputes than any other.
2. Supplier's item code. Your description says "M8 bolt." The supplier stocks twelve kinds. Their code removes the guess.
3. Delivery terms. If the PO does not say who pays freight, the freight shows up on the bill and you either pay it or argue about it.
4. The customer order reference. Without it, when the PO is late, nobody can say which customer to call.
5. Approval. A PO with no recorded approval is a spend nobody can trace back to a decision.
What the Template Cannot Do
A template records what you asked for. It cannot record what happened next, and that is where the money is:
- whether the supplier confirmed it, and the date they promised,
- what was received, per line, and when,
- what was billed, and whether it matched.
Those are tracked after the PO is sent. The process is in how to track purchase orders from creation to delivery, and the controls in procure-to-pay explained.
How Purchase Orders Work in Loopency
Every field above is on a Loopency purchase order, and the record carries on after the PO is sent:
- Numbering, supplier, delivery address, terms, currency and lines come from records you already keep: the supplier's details, your items, the supplier's price for that item. Supplier prices apply to new orders, and an order already placed keeps the price it was placed at.
- A PO can be raised from an approved requisition, carrying its lines, or from "Buy what's short" on a customer order, linked to that order.
- The supplier receives it as a secure link they can read without an account and ask questions on.
- Receipts, bills and the three-way match attach to the same PO, line by line.
- On the Business plan, you can configure approval policies for who must approve before a purchase goes ahead.
- Need a field that is not on the standard PO? You can extend the purchase order with your own fields, and they get the same permissions, history and reports as the built-in ones.
Where to Start
Compare your current PO template with the tables above and add the five fields if they are missing. That alone will cut receiving errors. If you want the PO to carry on after it is sent, start a free Loopency workspace, bring in your suppliers and items, and raise your next real PO there.